Between April and June 2026, Kverneland Aqua supported a maintenance and upgrade campaign onboard a Boskalis offshore construction vessel in Spain. The project focused on the removal of hydraulic cylinders from the vessel’s Launch and Recovery System (LARS), enabling refurbishment and upgrade work to be carried out at a specialized hydraulic workshop in the Netherlands before reinstallation and return to service.

The campaign was executed while coordinating multiple stakeholders, including vessel personnel, hydraulic specialists and logistics providers, ensuring minimal disruption to the vessel’s operational schedule.

01

Client

Boskalis

03

Date

2026

02

Our Role

Turnkey Upgrade Contractor

04

Project duration

8 weeks

Scoope Of Work

The scope included the controlled dismantling of hydraulic cylinders from the vessel’s LARS system, preparation for transportation, coordination with the refurbishment facility, and support during reinstallation and commissioning activities following return delivery.

Mechanical Dismantling of LARS Cylinders

Safe removal of hydraulic cylinders from the LARS system, including disassembly of mechanical connections and preparation for transport and refurbishment.

Hydraulic Isolation and Disconnection

Controlled isolation of the hydraulic system, pressure release, and disconnection of hydraulic lines to ensure safe removal and prevent contamination.

Lifting and Handling Operations Onboard

Planning and execution of lifting activities required to remove and handle heavy cylinders safely within the vessel's working environment.

Inspection of Mounting Arrangements and Interfaces

Inspection of mounting points, pins and structural interfaces to verify condition and ensure smooth reinstallation following refurbishment.