LARS Cylinder Replacement and Upgrade Campaign
Between April and June 2026, Kverneland Aqua supported a maintenance and upgrade campaign onboard a Boskalis offshore construction vessel in Spain. The project focused on the removal of hydraulic cylinders from the vessel’s Launch and Recovery System (LARS), enabling refurbishment and upgrade work to be carried out at a specialized hydraulic workshop in the Netherlands before reinstallation and return to service.
The campaign was executed while coordinating multiple stakeholders, including vessel personnel, hydraulic specialists and logistics providers, ensuring minimal disruption to the vessel’s operational schedule.
Client
Boskalis
Date
2026
Our Role
Turnkey Upgrade Contractor
Project duration
8 weeks
Scoope Of Work
The scope included the controlled dismantling of hydraulic cylinders from the vessel’s LARS system, preparation for transportation, coordination with the refurbishment facility, and support during reinstallation and commissioning activities following return delivery.
Mechanical Dismantling of LARS Cylinders
Hydraulic Isolation and Disconnection
Lifting and Handling Operations Onboard
Inspection of Mounting Arrangements and Interfaces